Grand Central Terminal is a multi-level facility dependent upon its elevators to transport materials, employees and customers between various levels. The majority of the elevators were placed in service over ninety years ago and have not seen significant rehabilitation since then. Other elevators were rehabilitated approximately fifteen years ago, but were heavily utilized during the terminal's renovation project, and now require rehabilitation.

VDA is providing vertical transportation consulting services for twenty-seven elevators (16 passenger and 11 freight), which require modification, rehabilitation or complete replacement.

Project Details
  • Client: Stantec
  • Status: Completion late 2007
  • Services provided: Modernization, New Equipment/Existing Building
  • VDA Office: Livingston, NJ